A Major Blow for Homebuyers? RERA's Ruling on Delay Compensation
A recent Haryana RERA ruling has set off a fresh debate among property buyers in Gurugram: if a builder is late with possession, how much can a buyer actually claim? The short answer from the Adjudicating Officer is that delay interest is the remedy for buyers who stay in the project, and no extra compensation can be claimed on top of it for the same delay. For anyone tracking projects such as MRG Crown Sector 106, this is a ruling worth understanding before you book.
What Did the Haryana RERA Adjudicating Officer Decide?
Adjudicating Officer Rajender Kumar of Haryana RERA held that an allottee who has already been awarded interest for delayed possession by the Authority cannot claim additional compensation before the Adjudicating Officer for the same delay.
In the case reported by LiveLaw and Outlook Money, the buyer argued that the delay interest granted by the Authority on 28 September 2021 was not enough. The builder countered that the same cause of action had already been decided, because delay interest had been awarded in an earlier complaint. The Adjudicating Officer agreed and dismissed the claim for further compensation.
Stay or Exit: The Two Remedies Under Section 18
The reasoning rests on how Section 18 of the RERA Act and the Haryana RERA Rules treat a delayed project. The ruling draws a clear line between two choices available to a buyer:
- Stay in the project: the buyer gets interest for every month of delay until possession is handed over.
- Exit the project: the buyer can seek a refund along with interest and compensation.
For buyers who stay, the interest is calculated at the State Bank of India's highest marginal cost of lending rate plus 2 percent. In such cases, that interest is treated as the full compensation for the delay.
Why the Ruling Is Being Called a Blow
The concern is easy to see. Buyers who accept possession cannot add separate claims such as mental anguish, price escalation or loss of property appreciation before the Adjudicating Officer once delay interest has been granted. Legal experts quoted by Outlook Money, including Adnan Siddiqui of King Stubb & Kasiva and Suresh Palav of IndiaLaw LLP, say builders are likely to rely on this reasoning to resist multiple compensation claims, and that buyers will need to decide carefully whether to stay or exit when possession is delayed.
Is It Really a Blow? The Other Side
It helps to look at what has not changed:
- Delay interest is still payable for every month of delay, so buyers are not left without a remedy.
- The exit route, with refund, interest and compensation, remains open.
- The Adjudicating Officer can award compensation only for violations of Sections 12, 14, 18 and 19, while matters like conveyance deeds go to the Authority.
Other Haryana RERA orders reported by LiveLaw have taken a similar view, so this is better read as a consistent position on delay compensation than a one-off surprise.
What Homebuyers Should Do Before Booking
- Check RERA registration: confirm the registration number, validity and the area covered on the Haryana RERA portal.
- Note the declared possession date: the date declared at registration is your reference point if a delay ever arises.
- Read the agreement carefully: understand your options before you choose to stay or exit.
- Keep records: payments, demand letters and correspondence all matter in a dispute.
As an example of what to verify, a part of MRG Crown in Sector 106, Gurugram is registered with HARERA under RERA-GRG-PROJ-1816-2024, with a declared completion date of 15 November 2027 for the registered portion. Because that registration covers only a part of the overall project, always confirm the details for the exact phase you are considering, and check updates on the developer's official website.
Frequently Asked Questions
Can a homebuyer claim extra compensation if delay interest is already granted?
According to the Haryana RERA Adjudicating Officer's ruling, no. Delay interest is treated as the compensation for the delay when the buyer stays in the project.
What if I want to leave the project instead?
A buyer who chooses to withdraw can seek a refund along with interest and compensation under Section 18.
What interest rate applies to delayed possession in Haryana?
The rate is the State Bank of India's highest marginal cost of lending rate plus 2 percent.
Where can I check the RERA status of MRG Crown?
You can search the project on the Haryana RERA portal, and the MRG Crown page on Coming Keys collects the key project details in one place.
Final Thoughts
So, is this a major blow for homebuyers? It narrows what a buyer can claim after choosing to stay, but it does not remove the right to delay interest or the option to exit. The practical lesson is to do your homework early. If you are researching MRG Crown Sector 106 or any other Gurugram project, verify the RERA details, note the declared possession date and understand your remedies before you commit.
This article is for general information only and is not legal advice. For a specific dispute, please consult a qualified lawyer.